Installation Guidelines for Brentwood StormTank Connection Accessories


These Installation Guidelines were written by Brentwood Industries, Inc. to inform contractors and other installers of the steps needed to safely and successfully install Brentwood StormTank Connection Accessories (Observataion Ports and Inlet/Outlet Connections). As every installation is unique, additional installation procedures may be required at a given site. The text and pictures shown here are for illustrative purposes only. Always check with the site owner/project engineer for their specific requirements. Contact your local StormTank distributor or Brentwood Industries for additional technical support, if required.

Inlet/Outlet Connectors
1. Cut hole in Side Panel


1. Cut Hole in Side Panel
Using a hole saw or jigsaw, cut a hole in the StormTank Side Panel in the same diameter as the inlet/outlet connector pipe. Before cutting, make sure the center of the proposed hole is located at the correct elevation and that the flange plate of the connector does not extend beyond the side panel edges.

2. Attach Connector to Side Panel


2. Attach Connector to Side Panel
Attach the connector to the side panel using cable ties through the holes in the corners of the flange plate. Make sure the longer length of the inlet/outlet connector pipe is on the outside of the StormTank system to allow for joining the drain pipe.

3. Cover with Geotextile and/or Lner


3. Cover with Geotextile and/or Liner
Cover the connector flange plate with geotextile and/or liner material and seal with banding or water-resistant tape.

Observation Ports
1. Cut hole in top panel


1. Cut Hole in Top Panel
Using a hole saw or jigsaw, cut a hole in the center of the StormTank Module Top Panel in the same diameter as the observation port pipe.

2. Align Port Plate with Top Panel


2. Align Port Plate with Top Panel
Insert two StormTank Vertical Connectors into the circular recesses of the top panel of the StormTank module and align the port plate using the matching holes in the plate.

Make sure that the plate is positioned so that the corners of the plate extend across the two adjoining modules.

3. Cover with Geotextile and/or Liner


3. Cover with Geotextile and/or Liner
Cover the port plate with geotextile and/or liner material and seal with banding or water-resistant tape.

Connection Accessories Dimensions
OBSERVATION PORTS
StormTank Observation Ports
PIPE
DIAMETER
PIPE
LENGTH
PLATE
DIMENSIONS
PLATE
THICKNESS
4"
(102 mm)
11.25"
(286 mm)
18" x 18"
(457 mm x 457 mm)
0.50"
(13 mm)
6"
(152 mm)
11.25"
(286 mm)
18" x 18"
(457 mm x 457 mm)
0.50"
(13 mm)
INLET /OUTLET CONNECTORS
StormTank Inlet/Outlet Connection
12"
(305 mm)
11.25"
(286 mm)
18" x 18"
(457 mm x 457 mm)
0.25"
(6 mm)
14"
(356 mm)
11.25"
(286 mm)
18" x 18"
(457 mm x 457 mm)
0.25"
(6 mm)


All of the information, observations, and recommendations provided in these guidelines are being furnished only as a matter of general information and are not in any way intended as a guarantee on the part of Brentwood Industries, Inc., Reading, PA.


Top of Page

Home | Applications |Products | Installations | Product Specifications | Process Design Requests | Installation Guidelines | Contact | Publications

Copyright © 2010 Brentwood Industries, Inc.